NPP units repair duration

NPP units repair duration

Download dataset

Description
Data sample
Fields description
Files

Information on the planned and actual duration of current, medium and major repairs and the reserve shutdown of nuclear power plants (NPPs). Information is presented by type of repair for specific power units, indicating the date on which the shutdown of the power unit began and ended for repair or reserve purposes, as well as the number of days during which the repair or reserve lasted.

Data for period

Nov. 7, 2017 - Dec. 31, 2021

Update frequency

Quarterly

Unique identifier

c2a8a12b-d186-4249-8cfd-f89f5a845199
Actual repair start dateActual (forecast) repair end dateNuclear power station nameNPP unit numberRepair typeActual (forecast) repair duration, days
2017-11-072018-02-07KhNPP1major92.59
2017-11-122018-01-14ZNPP6major63.67
2017-12-082018-07-23RNPP3medium227.09
2017-12-302018-02-06RNPP1medium39
2018-01-032018-01-08KhNPP2current5.56
FieldNameDescription
date_startActual repair start date
date_endActual (forecast) repair end date
power_plant_nameNuclear power station name• ZNPP - Zaporizhzhia NPP (Nuclear Power Plant) • RNPP - Rivne NPP • KhNPP - Khmelnytskyi NPP • SUNPP - South-Ukraine NPP
unit_numberNPP unit number
repair_typeRepair typeCurrent / medium / major
repair_durationActual (forecast) repair duration, daysdays
NameUpdate dateLines numberSizeFormatDownload

2021_12_31_uk_tryvalist_remontu_aes.csv

99

5.79 kB

UK
CSV

2021_12_31_uk_tryvalist_remontu_aes.xlsx

99

8.46 kB

UK
XLSX

2021_12_31_en_tryvalist_remontu_aes.csv

99

4.34 kB

EN
CSV

2021_12_31_en_tryvalist_remontu_aes.xlsx

99

8.21 kB

EN
XLSX